Bramford GEC (Ethos Green)
Bramford GEC (Ethos Green) is a storage, solar project of 650 MW in NESO's TEC Register of 23 Oct 2026, connecting at Bramford B 400kV Substation (NGET). Status: Awaiting Consents. Gate 1.
- Customer
- BRAMFORD GREEN ENERGY CENTRE LTD
- Connection site
- Bramford B 400kV Substation
- Transmission owner
- NGET
- Technology
- Storage, Solar
- Capacity (TEC)
- 650 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Awaiting Consents
- MW effective from
- 1 Jun 2032
- NESO project number
- PRO-004027
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.