Bramford 400kV Substation
Bramford 400kV Substation (NGET) has 8 projects in NESO's TEC Register of 23 Oct 2026: 1,163 MW in the queue, 749 MW Gate 1, and 147.9 MW connected. Contracted capacity, not headroom.
- Transmission owner
- NGET
- Projects
- 8
- MW in the queue
- 1,163 MW
- Gate 1 MW
- 749 MW
- MW connected
- 147.9 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 7 | 1,270 |
| Solar | 4 | 420 |
| Bioenergy | 1 | 41 |
Projects at Bramford 400kV Substation
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Alcemi Bramford Battery Energy Storage Facility | Storage | 500 | Gate 1 | Scoping | 30 Oct 2030 |
| Bramford BESS | Storage | 300 | Consents Approved | 30 Nov 2029 | |
| ER BRF 2 Energy | Storage, Solar | 249 | Gate 1 | Scoping | 30 Jul 2033 |
| Bramford (Tertiary) | Storage, Solar | 57 | Built | ||
| Bramford 2 GEC (Ethos Green) | Storage, Solar | 57 | Awaiting Consents | 1 Jul 2032 | |
| Bramford Tertiary | Storage, Solar | 49.9–57 | Consents Approved | 16 Jul 2026, 1 Oct 2029 | |
| Brook Farm BESS | Storage | 49.9 | Built | ||
| Thetford | Bioenergy | 41 | Built |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.