Alcemi Bramford Battery Energy Storage Facility
Alcemi Bramford Battery Energy Storage Facility is a storage project of 500 MW in NESO's TEC Register of 23 Oct 2026, connecting at Bramford 400kV Substation (NGET). Status: Scoping. Gate 1.
- Customer
- ALCEMI STORAGE DEVELOPMENTS 1 LIMITED
- Connection site
- Bramford 400kV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 500 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 30 Oct 2030
- NESO project number
- PRO-001416
Also at Bramford 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Bramford (Tertiary) | Storage, Solar | 57 |
| Bramford 2 GEC (Ethos Green) | Storage, Solar | 57 |
| Bramford BESS | Storage | 300 |
| Bramford Tertiary | Storage, Solar | 49.9–57 |
| Brook Farm BESS | Storage | 49.9 |
| ER BRF 2 Energy | Storage, Solar | 249 |
| Thetford | Bioenergy | 41 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.