Braintree 400kV Substation

Braintree 400kV Substation (NGET) has 6 projects in NESO's TEC Register of 23 Oct 2026: 1,657 MW in the queue, 57 MW of it Gate 2, 1,550 MW Gate 1, and 55 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
6
MW in the queue
1,657 MW
Gate 2 MW
57 MW
Gate 1 MW
1,550 MW
MW connected
55 MW
Earliest confirmed date
30 May 2027

By technology

TechnologyProjectsMW
Solar51,657
Storage51,657
Energy from waste155

Projects at Braintree 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
BraintreeStorage, Solar1,000Gate 1Scoping31 Oct 2034
Bulls Lodge Farm 2Storage, Solar350Gate 1Scoping30 Mar 2033
Bulls Lodge FarmStorage, Solar200Gate 1Scoping30 Apr 2033
BraintreeStorage, Solar57Gate 2Consents Approved30 May 2027
Indaver Rivenhall IWMFEnergy from waste55Built
Braintree (Tertiary)Storage, Solar49.9Consents Approved30 Oct 2026