Braintree (Tertiary)

Braintree (Tertiary) is a storage, solar project of 49.9 MW in NESO's TEC Register of 23 Oct 2026, connecting at Braintree 400kV Substation (NGET). Status: Consents Approved.

Customer
CSE22 LIMITED
Connection site
Braintree 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
49.9 MW
Agreement
Direct Connection
Status
Consents Approved
MW effective from
30 Oct 2026
NESO project number
PRO-001043

Also at Braintree 400kV Substation

ProjectTechnologyMW
BraintreeStorage, Solar1,000
BraintreeStorage, Solar57
Bulls Lodge FarmStorage, Solar200
Bulls Lodge Farm 2Storage, Solar350
Indaver Rivenhall IWMFEnergy from waste55