Borders Connection Node A 400kV (NGET) has 2 projects in NESO's TEC Register of 23 Oct 2026: 440 MW in the queue, 440 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
2
MW in the queue
440 MW
Gate 1 MW
440 MW
MW connected
0 MW

By technology

TechnologyProjectsMW
Storage2440
Solar1240

Projects at Borders Connection Node A 400kV

ProjectTechnologyMWGateStatusMW effective from
Middle Farm ChollertonStorage, Solar240Gate 1Scoping30 Oct 2035
Lynefield BESSStorage200Gate 1Scoping30 Oct 2035