Grid GuardianOpen the evidence in the app

Lynefield BESS

Lynefield BESS is a storage project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at Borders Connection Node A 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
WINDEL GRID 1 LIMITED
Connection site
Borders Connection Node A 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
200 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Oct 2035
NESO project number
PRO-003555

Also at Borders Connection Node A 400kV Substation

ProjectTechnologyMW
Middle Farm ChollertonStorage, Solar240