Bonnybridge 132/33kV
Bonnybridge 132/33kV (SPT) has 2 projects in NESO's TEC Register of 23 Oct 2026: 90 MW in the queue, 60 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.
- Transmission owner
- SPT
- Projects
- 2
- MW in the queue
- 90 MW
- Gate 1 MW
- 60 MW
- MW connected
- 0 MW
By technology
| Technology | Projects | MW |
|---|---|---|
| Storage | 1 | 60 |
| Onshore wind | 1 | 30 |
Projects at Bonnybridge 132/33kV
| Project | Technology | MW | Gate | Status | MW effective from |
|---|---|---|---|---|---|
| Scottish Water Bonnybridge STW 60MW BESS | Storage | 60 | Gate 1 | Scoping | 31 Oct 2030 |
| Drummarnock Wind Farm | Onshore wind | 30 | Scoping | 1 Oct 2026 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.