Scottish Water Bonnybridge STW 60MW BESS
Scottish Water Bonnybridge STW 60MW BESS is a storage project of 60 MW in NESO's TEC Register of 23 Oct 2026, connecting at Bonnybridge 132/33kV (SPT). Status: Scoping. Gate 1.
- Customer
- Bluestone Energy Ltd
- Connection site
- Bonnybridge 132/33kV
- Transmission owner
- SPT
- Technology
- Storage
- Capacity (TEC)
- 60 MW
- Agreement
- Embedded
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 31 Oct 2030
- NESO project number
- PRO-002410