Blackhillock 275kV Substation

Blackhillock 275kV Substation (SHET) has 5 projects in NESO's TEC Register of 23 Oct 2026: 1,011 MW in the queue, 349 MW of it Gate 2, 400 MW Gate 1, and 0 MW connected. Contracted capacity, not headroom.

Transmission owner
SHET
Projects
5
MW in the queue
1,011 MW
Gate 2 MW
349 MW
Gate 1 MW
400 MW
MW connected
0 MW
Earliest confirmed date
31 Oct 2028

By technology

TechnologyProjectsMW
Storage41,199
Solar1150
Demand1112.2
Onshore wind1112.2

Projects at Blackhillock 275kV Substation

ProjectTechnologyMWGateStatusMW effective from
Keith BESS StationStorage400Gate 1Scoping31 Oct 2033
Blackhillock BatteryStorage349Gate 2Consents Approved31 Oct 2028
Zenobe Blackhillock 300 MWStorage200–300Built, Consents Approved1 Apr 2026
Kedrum Solar FarmStorage, Solar150Awaiting Consents30 May 2030
Teindland Wind FarmDemand, Onshore wind112.2Awaiting Consents28 Sept 2029