Blackhillock Battery
Blackhillock Battery is a storage project of 349 MW in NESO's TEC Register of 23 Oct 2026, connecting at Blackhillock 400kV Substation (SHET). Status: Consents Approved. Gate 2.
- Customer
- BLACKHILLOCK FLEXPOWER LTD
- Connection site
- Blackhillock 400kV Substation
- Transmission owner
- SHET
- Technology
- Storage
- Capacity (TEC)
- 349 MW
- Agreement
- Direct Connection
- Gate
- Gate 2
- Status
- Consents Approved
- MW effective from
- 31 Oct 2028
- NESO project number
- PRO-001970
Also at Blackhillock 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Kedrum Solar Farm | Storage, Solar | 150 |
| Keith BESS Station | Storage | 400 |
| Teindland Wind Farm | Demand, Onshore wind | 112.2 |
| Zenobe Blackhillock 300 MW | Storage | 200–300 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.