Alverdiscott 400kV Substation

Alverdiscott 400kV Substation (NGET) has 16 projects in NESO's TEC Register of 23 Oct 2026: 13,316 MW in the queue, 4,500 MW Gate 1, and 30 MW connected. Contracted capacity, not headroom.

Transmission owner
NGET
Projects
16
MW in the queue
13,316 MW
Gate 1 MW
4,500 MW
MW connected
30 MW

By technology

TechnologyProjectsMW
Offshore wind1312,216
Storage31,130
Solar11,000

Projects at Alverdiscott 400kV Substation

ProjectTechnologyMWGateStatusMW effective from
GallosOffshore wind2,000Scoping6 Dec 2036
Merlin 2 Offshore WindfarmOffshore wind1,500Gate 1Scoping31 Oct 2031
SSE Celtic Sea 1Offshore wind1,500Scoping6 Dec 2036
Cormoran Offshore Wind FarmOffshore wind1,008Scoping6 Dec 2036
Mererid Offshore Wind FarmOffshore wind1,008Scoping6 Dec 2036
Alverdiscott FarmStorage, Solar1,000Scoping24 Apr 2037
Celtic 2 Offshore Wind FarmOffshore wind1,000Gate 1Scoping31 Oct 2031
Equinor Celtic Sea 1Offshore wind1,000Gate 1Scoping6 Dec 2036
Gwynt Glas Offshore Wind Farm 2Offshore wind1,000Scoping6 Dec 2036
Petroc Extension Offshore Wind FarmOffshore wind1,000Scoping6 Dec 2036
Gwynt Glas Offshore Wind FarmOffshore wind300Gate 1Scoping31 Oct 2031
Merlin Offshore Wind FarmOffshore wind300Gate 1Scoping30 Oct 2031
Morwind 300Offshore wind300Scoping31 Oct 2031
Petroc Offshore Wind FarmOffshore wind300Gate 1Scoping31 Mar 2026
AlverdiscottStorage49.9–100Gate 1Scoping31 Aug 2031, 31 Oct 2036
Care North Tawton BEGAStorage30Built