Worset PV & BESS Park
Worset PV & BESS Park is a storage, solar project of 37.5 MW in NESO's TEC Register of 23 Oct 2026, connecting at Hartmoor 275kV Substation (NGET). Status: Under Construction/Commissioning. Gate 2.
- Customer
- Worcestershire Solar 1 Limited
- Connection site
- Hartmoor 275kV Substation
- Transmission owner
- NGET
- Technology
- Storage, Solar
- Capacity (TEC)
- 37.5 MW
- Agreement
- Direct Connection
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- MW effective from
- 30 Oct 2027
- NESO project number
- PRO-001055
Also at Hartmoor 275kV Substation
| Project | Technology | MW |
|---|---|---|
| Martindale Farm | Storage, Solar, Onshore wind | 239.9 |
| WORSET LANE BESS | Storage | 200 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.