WORSET LANE BESS

WORSET LANE BESS is a storage project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at Hartmoor 275kV Substation (NGET). Status: Consents Approved. Gate 2.

Customer
FIELD HARTMOOR LTD
Connection site
Hartmoor 275kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
200 MW
Agreement
Direct Connection
Gate
Gate 2
Status
Consents Approved
MW effective from
31 May 2029
NESO project number
PRO-003650

Also at Hartmoor 275kV Substation

ProjectTechnologyMW
Martindale FarmStorage, Solar, Onshore wind239.9
Worset PV & BESS ParkStorage, Solar37.5