West Burton B
West Burton B is a gas, storage project of 1,833–1,881 MW in NESO's TEC Register of 23 Oct 2026, connecting at West Burton 400kV Substation (NGET). Status: Built.
- Customer
- WEST BURTON B LIMITED
- Connection site
- West Burton 400kV Substation
- Transmission owner
- NGET
- Technology
- Gas, Storage
- Capacity (TEC)
- 1,833–1,881 MW
- Agreement
- Direct Connection
- Status
- Built
- MW effective from
- 30 Oct 2027, 30 Oct 2034
- NESO project number
- PRO-000369-1, PRO-000369-2
Also at West Burton 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Steeple Solar Farm | Storage, Solar | 600 |
| West Burton | Storage, Solar | 120 |
| West Burton Solar Project | Storage, Solar | 480 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.