Grid GuardianOpen the evidence in the app

Steeple Solar Farm

Steeple Solar Farm is a storage, solar project of 600 MW in NESO's TEC Register of 23 Oct 2026, connecting at West Burton 400kV Substation (NGET). Status: Scoping.

Customer
Steeple Solar Farm Limited
Connection site
West Burton 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
600 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
31 Oct 2029
NESO project number
PRO-001945

Also at West Burton 400kV Substation

ProjectTechnologyMW
West BurtonStorage, Solar120
West Burton BGas, Storage1,833–1,881
West Burton Solar ProjectStorage, Solar480

Source