UPPER GREENFIELDS BESS
UPPER GREENFIELDS BESS is a storage project of 175 MW in NESO's TEC Register of 23 Oct 2026, connecting at New Deer 2 132kV Substation (SHET). Status: Scoping. Gate 1.
- Customer
- S4 UK DEV LTD
- Connection site
- New Deer 2 132kV Substation
- Transmission owner
- SHET
- Technology
- Storage
- Capacity (TEC)
- 175 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 31 Oct 2033
- NESO project number
- PRO-003682
Also at New Deer 2 132kV Substation
| Project | Technology | MW |
|---|---|---|
| L48 BESS Burnside | Storage | 200 |
| New Deer 2 BESS | Storage | 200 |
| New Deer Battery Storage | Storage | 500 |
| New Deer BESS Station | Storage | 500 |
| Peterhead PV and BESS Station | Storage, Solar | 480 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.