Grid GuardianOpen the evidence in the app

Peterhead PV and BESS Station

Peterhead PV and BESS Station is a storage, solar project of 480 MW in NESO's TEC Register of 23 Oct 2026, connecting at New Deer 2 400kV Substation (SHET). Status: Awaiting Consents.

Customer
ETP UK 2 LTD
Connection site
New Deer 2 400kV Substation
Transmission owner
SHET
Technology
Storage, Solar
Capacity (TEC)
480 MW
Agreement
Direct Connection
Status
Awaiting Consents
MW effective from
31 Oct 2033
NESO project number
PRO-002775

Also at New Deer 2 400kV Substation

ProjectTechnologyMW
L48 BESS BurnsideStorage200
New Deer 2 BESSStorage200
New Deer Battery StorageStorage500
New Deer BESS StationStorage500
UPPER GREENFIELDS BESSStorage175

Source