Tyler Hill Iver

Tyler Hill Iver is a storage project of 199.92 MW in NESO's TEC Register of 23 Oct 2026, connecting at London West Connection Node A 400kV Substation (NGET). Status: Awaiting Consents. Gate 1.

Customer
FRV Powertek Limited
Connection site
London West Connection Node A 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
199.92 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Awaiting Consents
MW effective from
31 Oct 2038
NESO project number
PRO-004134