Trafford 2 BESS
Trafford 2 BESS is a storage project of 1,400 MW in NESO's TEC Register of 23 Oct 2026, connecting at Carrington 400KV Substation (NGET). Status: Scoping.
- Customer
- FUTURE POINT MANCHESTER LIMITED
- Connection site
- Carrington 400KV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 1,400 MW
- Agreement
- Direct Connection
- Status
- Scoping
- MW effective from
- 30 Oct 2038
- NESO project number
- PRO-004992
Also at Carrington 400KV Substation
| Project | Technology | MW |
|---|---|---|
| Carrington | Storage | 680 |
| Carrington | Storage | 57 |
| Cryogenic Battery System (Synchronous) | Storage, Reactive Compensation | 0–49.9 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.