Cryogenic Battery System (Synchronous) is a storage, reactive compensation project of 0–49.9 MW in NESO's TEC Register of 23 Oct 2026, connecting at Carrington 400KV Substation (NGET). Status: Under Construction/Commissioning.
- Customer
- CRYOBATTERY ONE LIMITED
- Connection site
- Carrington 400KV Substation
- Transmission owner
- NGET
- Technology
- Storage, Reactive Compensation
- Capacity (TEC)
- 0–49.9 MW
- Agreement
- Direct Connection
- Status
- Under Construction/Commissioning
- MW effective from
- 8 May 2026, 8 Nov 2026
- NESO project number
- PRO-000549-1, PRO-000549-2