Staythorpe C
Staythorpe C is a gas, demand project of 1,752 MW in NESO's TEC Register of 23 Oct 2026, connecting at Staythorpe 400kV Substation (NGET). Status: Built.
- Customer
- RWE Generation UK Plc
- Connection site
- Staythorpe 400kV Substation
- Transmission owner
- NGET
- Technology
- Gas, Demand
- Capacity (TEC)
- 1,752 MW
- Agreement
- Direct Connection
- Status
- Built
- NESO project number
- PRO-000057
Also at Staythorpe 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Field Farm | Storage | 249.9 |
| Flash Solar Farm | Storage, Solar | 360–800 |
| Staythorpe | Storage, Solar | 400 |
| Staythorpe (BESS and PV) | Storage, Solar | 437 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.