Grid GuardianOpen the evidence in the app

Staythorpe

Staythorpe is a storage, solar project of 400 MW in NESO's TEC Register of 23 Oct 2026, connecting at Staythorpe 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
ENSO GREEN HOLDINGS X LIMITED
Connection site
Staythorpe 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
400 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2030
NESO project number
PRO-002083

Also at Staythorpe 400kV Substation

ProjectTechnologyMW
Field FarmStorage249.9
Flash Solar FarmStorage, Solar360–800
Staythorpe (BESS and PV)Storage, Solar437
Staythorpe CGas, Demand1,752