Sellafield
Sellafield is a chp (combined heat and power) project of 155 MW in NESO's TEC Register of 23 Oct 2026, connecting at Hutton 132kV Substation (NGET). Status: Built.
- Customer
- NUCLEAR DECOMMISSIONING AUTHORITY
- Connection site
- Hutton 132kV Substation
- Transmission owner
- NGET
- Technology
- CHP (Combined Heat and Power)
- Capacity (TEC)
- 155 MW
- Agreement
- Embedded
- Status
- Built
- NESO project number
- PRO-000219
Also at Hutton 132kV Substation
| Project | Technology | MW |
|---|---|---|
| Eskrigg End BESS | Storage | 249 |
| Hutton Battery Storage | Storage | 10 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.