Eskrigg End BESS

Eskrigg End BESS is a storage project of 249 MW in NESO's TEC Register of 23 Oct 2026, connecting at Hutton 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
Energi Generation 6 Ltd
Connection site
Hutton 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
249 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
1 Nov 2037
NESO project number
PRO-002804

Also at Hutton 400kV Substation

ProjectTechnologyMW
Hutton Battery StorageStorage10
SellafieldCHP (Combined Heat and Power)155