Grid GuardianOpen the evidence in the app

Pillswood BESS Phase 1

Pillswood BESS Phase 1 is a storage project of 49.9 MW in NESO's TEC Register of 23 Oct 2026, connecting at Creyke Beck GSP (NGET). Status: Built.

Customer
HEIT PW LIMITED
Connection site
Creyke Beck GSP
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
49.9 MW
Agreement
Embedded
Status
Built
NESO project number
PRO-001905

Also at Creyke Beck GSP

ProjectTechnologyMW
Bute Hydrogen Project 2Gas3,600
CREYKE BECKStorage, Solar500
Creyke Beck Battery 2Storage28.5
Creyke Beck PV & BESS SubStorage, Solar249.9
Creyke Beck Solar FarmSolar320
Flinton RoadStorage, Solar600
Hall Ings Farm SubstationSolar100
Hornsea Power Station 4Offshore wind1,500–2,600
KENLEY HOUSE SOLAR PARKSolar150
Pillswood BESS Phase 2Storage49.9