Creyke Beck Battery 2
Creyke Beck Battery 2 is a storage project of 28.5 MW in NESO's TEC Register of 23 Oct 2026, connecting at Creyke Beck 400kV Substation (NGET). Status: Consents Approved.
- Customer
- CBB SPV LIMITED
- Connection site
- Creyke Beck 400kV Substation
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 28.5 MW
- Agreement
- Direct Connection
- Status
- Consents Approved
- MW effective from
- 30 Jun 2028
- NESO project number
- PRO-004060
Also at Creyke Beck 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Bute Hydrogen Project 2 | Gas | 3,600 |
| CREYKE BECK | Storage, Solar | 500 |
| Creyke Beck PV & BESS Sub | Storage, Solar | 249.9 |
| Creyke Beck Solar Farm | Solar | 320 |
| Flinton Road | Storage, Solar | 600 |
| Hall Ings Farm Substation | Solar | 100 |
| Hornsea Power Station 4 | Offshore wind | 1,500–2,600 |
| KENLEY HOUSE SOLAR PARK | Solar | 150 |
| Pillswood BESS Phase 1 | Storage | 49.9 |
| Pillswood BESS Phase 2 | Storage | 49.9 |
Source