Grid GuardianOpen the evidence in the app

Ninfield Greener Grid Park

Ninfield Greener Grid Park is a storage, reactive compensation project of 0–450 MW in NESO's TEC Register of 23 Oct 2026, connecting at Ninfield 400kV Substation (NGET). Status: Awaiting Consents, Scoping.

Customer
Ninfield Grid Solutions Limited
Connection site
Ninfield 400kV Substation
Transmission owner
NGET
Technology
Storage, Reactive Compensation
Capacity (TEC)
0–450 MW
Agreement
Direct Connection
Status
Awaiting Consents, Scoping
MW effective from
30 Apr 2027, 31 Jan 2031, 31 Oct 2037
NESO project number
PRO-001756-1, PRO-001756-2, PRO-001756-3

Also at Ninfield 400kV Substation

ProjectTechnologyMW
CatsfieldStorage240
Ninfield Green Energy CentreDemand, Storage, Solar600
Saver & Pashley Farm Energy ParkStorage, Solar129.9

Source