Catsfield
Catsfield is a storage project of 240 MW in NESO's TEC Register of 23 Oct 2026, connecting at Ninfield GSP (NGET). Status: Scoping.
- Customer
- MAS 001 Limited
- Connection site
- Ninfield GSP
- Transmission owner
- NGET
- Technology
- Storage
- Capacity (TEC)
- 240 MW
- Agreement
- Embedded
- Status
- Scoping
- MW effective from
- 9 Nov 2037
- NESO project number
- PRO-004143
Also at Ninfield GSP
| Project | Technology | MW |
|---|---|---|
| Ninfield Green Energy Centre | Demand, Storage, Solar | 600 |
| Ninfield Greener Grid Park | Storage, Reactive Compensation | 0–450 |
| Saver & Pashley Farm Energy Park | Storage, Solar | 129.9 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.