Grid GuardianOpen the evidence in the app

Mount Pleasant

Mount Pleasant is a storage project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at Warwickshire Connection Node A 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
HARMONY ENERGY LIMITED
Connection site
Warwickshire Connection Node A 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
200 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
31 Oct 2037
NESO project number
PRO-005962

Also at Warwickshire Connection Node A 400kV Substation

ProjectTechnologyMW
Bellbroughton Energy ParkStorage, Solar500
Dunclent Battery StorageStorage400

Source