Dunclent Battery Storage

Dunclent Battery Storage is a storage project of 400 MW in NESO's TEC Register of 23 Oct 2026, connecting at Warwickshire Connection Node A 400kV Substation (NGET). Status: Scoping. Gate 1.

Customer
Firma Vogt Solar Ltd
Connection site
Warwickshire Connection Node A 400kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
400 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
30 Oct 2037
NESO project number
PRO-002827