Grid GuardianOpen the evidence in the app

Lovat Estate BESS

Lovat Estate BESS is a storage project of 49.9 MW in NESO's TEC Register of 23 Oct 2026, connecting at Beauly 132/33 kV GSP Substation (SHET). Status: Consents Approved. Gate 2.

Customer
LG-B-50a Limited
Connection site
Beauly 132/33 kV GSP Substation
Transmission owner
SHET
Technology
Storage
Capacity (TEC)
49.9 MW
Agreement
Embedded
Gate
Gate 2
Status
Consents Approved
MW effective from
31 May 2026
NESO project number
PRO-003062

Also at Beauly 132/33 kV GSP Substation

ProjectTechnologyMW
Farr Wind Farm - TomatinOnshore wind92
Tarvie Wind FarmStorage, Onshore wind77

Source