Farr Wind Farm - Tomatin
Farr Wind Farm - Tomatin is a onshore wind project of 92 MW in NESO's TEC Register of 23 Oct 2026, connecting at Beauly GSP (SHET). Status: Built.
- Customer
- FARR WINDFARM LIMITED
- Connection site
- Beauly GSP
- Transmission owner
- SHET
- Technology
- Onshore wind
- Capacity (TEC)
- 92 MW
- Agreement
- Direct Connection
- Status
- Built
- NESO project number
- PRO-000156
Also at Beauly GSP
| Project | Technology | MW |
|---|---|---|
| Lovat Estate BESS | Storage | 49.9 |
| Tarvie Wind Farm | Storage, Onshore wind | 77 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.