Lochore BESS
Lochore BESS is a storage project of 900 MW in NESO's TEC Register of 23 Oct 2026, connecting at Westfield 132/33kV (SPT). Status: Scoping. Gate 1.
- Customer
- LOCHORE BESS LTD
- Connection site
- Westfield 132/33kV
- Transmission owner
- SPT
- Technology
- Storage
- Capacity (TEC)
- 900 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 31 Oct 2031
- NESO project number
- PRO-003483
Also at Westfield 132/33kV
| Project | Technology | MW |
|---|---|---|
| Brunt Hill Wind Farm | Storage, Onshore wind | 99 |
| Fife 2 BESS | Storage | 49.9 |
| Fife Battery Storage | Storage | 200 |
| Kirklands Farm BESS | Storage | 200 |
| Westfield BESS | Storage | 350 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.