Grid GuardianOpen the evidence in the app

Fife Battery Storage

Fife Battery Storage is a storage project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at Westfield 132/33kV (SPT). Status: Scoping.

Customer
CARLTON POWER LIMITED
Connection site
Westfield 132/33kV
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
200 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
30 Oct 2031
NESO project number
PRO-001888

Also at Westfield 132/33kV

ProjectTechnologyMW
Brunt Hill Wind FarmStorage, Onshore wind99
Fife 2 BESSStorage49.9
Kirklands Farm BESSStorage200
Lochore BESSStorage900
Westfield BESSStorage350

Source