Grid GuardianOpen the evidence in the app

Lister Drive

Lister Drive is a storage project of 20 MW in NESO's TEC Register of 23 Oct 2026, connecting at Lister Drive 132kV Substation (NGET). Status: Built.

Customer
ORSTED ESS MERSEY LIMITED
Connection site
Lister Drive 132kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
20 MW
Agreement
Embedded
Status
Built
NESO project number
PRO-001257

Also at Lister Drive 132kV Substation

ProjectTechnologyMW
Lister Battery (formerly Lister Drive)Storage57
Lister Drive 275kVReactive Compensation0
Lister Drive ShawStorage57