Lister Battery (formerly Lister Drive)

Lister Battery (formerly Lister Drive) is a storage project of 57 MW in NESO's TEC Register of 23 Oct 2026, connecting at Lister Drive 275kV Substation (NGET). Status: Consents Approved. Gate 2.

Customer
LISTER BATTERY LTD
Connection site
Lister Drive 275kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
57 MW
Agreement
Direct Connection
Gate
Gate 2
Status
Consents Approved
MW effective from
30 Sept 2029
NESO project number
PRO-001088