Holmston Farm Battery Energy Storage System

Holmston Farm Battery Energy Storage System is a storage project of 49.9 MW in NESO's TEC Register of 23 Oct 2026, connecting at Ayr 275/33kV (SPT). Status: Under Construction/Commissioning. Gate 2.

Customer
Field Holmston Ltd
Connection site
Ayr 275/33kV
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
49.9 MW
Agreement
Embedded
Gate
Gate 2
Status
Under Construction/Commissioning
MW effective from
31 Jul 2026
NESO project number
PRO-002359