Clonmacate Farm BESS

Clonmacate Farm BESS is a storage project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at Ayr 275/33kV (SPT). Status: Scoping.

Customer
GPC Project 11 Ltd
Connection site
Ayr 275/33kV
Transmission owner
SPT
Technology
Storage
Capacity (TEC)
200 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
31 Oct 2030
NESO project number
PRO-003421

Also at Ayr 275/33kV

ProjectTechnologyMW
Ayr Energy StorageStorage150
FPE Ayr BESSStorage200
Holmston Farm Battery Energy Storage SystemStorage49.9
Knockkippen Energy ParkDemand, Storage, Solar, Onshore wind60