Fawley CHP

Fawley CHP is a chp (combined heat and power) project of 158 MW in NESO's TEC Register of 23 Oct 2026, connecting at Fawley 400kV Substation (NGET). Status: Built.

Customer
ESSO PETROLEUM COMPANY,LIMITED
Connection site
Fawley 400kV Substation
Transmission owner
NGET
Technology
CHP (Combined Heat and Power)
Capacity (TEC)
158 MW
Agreement
Embedded
Status
Built
NESO project number
PRO-000157

Also at Fawley 400kV Substation

ProjectTechnologyMW
Copper Nose BESSStorage150
CowesGas140
KXP Alpha OneStorage99.99
KXP Alpha ThreeStorage99.99
KXP Alpha TwoStorage99.99
Lynes CommonGas49.9
Manor Farm Solar ParkStorage, Solar150

Source