Copper Nose BESS

Copper Nose BESS is a storage project of 150 MW in NESO's TEC Register of 23 Oct 2026, connecting at Fawley 132kV Substation (NGET). Status: Scoping. Gate 1.

Customer
Copper Nose Energy Ltd
Connection site
Fawley 132kV Substation
Transmission owner
NGET
Technology
Storage
Capacity (TEC)
150 MW
Agreement
Direct Connection
Gate
Gate 1
Status
Scoping
MW effective from
24 Oct 2036
NESO project number
PRO-002356