Grid GuardianOpen the evidence in the app

EcoGrimsbyWest

EcoGrimsbyWest is a storage, solar project of 249 MW in NESO's TEC Register of 23 Oct 2026, connecting at Grimsby West 400kV Substation (NGET). Status: Scoping.

Customer
Econergy International Limited
Connection site
Grimsby West 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
249 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
30 Oct 2033
NESO project number
PRO-002251

Also at Grimsby West 400kV Substation

ProjectTechnologyMW
Bute Hydrogen Project 3Gas3,600
Carbon Free 2030Storage, Solar500
Great Coates BESSStorage300
Grimsby BESSStorage500
North Ray Solar Farm 2Solar180
STALLINGBOROUGH CARBON CAPTURE CCGTGas, Demand906
Stallingborough PV & BESS StationStorage, Solar500
West Grimsby FarmSolar150

Source