Carbon Free 2030
Carbon Free 2030 is a storage, solar project of 500 MW in NESO's TEC Register of 23 Oct 2026, connecting at Grimsby West 400kV Substation (NGET). Status: Scoping.
- Customer
- CARBON FREE 2030 ENERGY LIMITED
- Connection site
- Grimsby West 400kV Substation
- Transmission owner
- NGET
- Technology
- Storage, Solar
- Capacity (TEC)
- 500 MW
- Agreement
- Direct Connection
- Status
- Scoping
- MW effective from
- 30 Jun 2034
- NESO project number
- PRO-003047
Also at Grimsby West 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Bute Hydrogen Project 3 | Gas | 3,600 |
| EcoGrimsbyWest | Storage, Solar | 249 |
| Great Coates BESS | Storage | 300 |
| Grimsby BESS | Storage | 500 |
| North Ray Solar Farm 2 | Solar | 180 |
| STALLINGBOROUGH CARBON CAPTURE CCGT | Gas, Demand | 906 |
| Stallingborough PV & BESS Station | Storage, Solar | 500 |
| West Grimsby Farm | Solar | 150 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.