Didcot Farm
Didcot Farm is a storage, solar project of 200 MW in NESO's TEC Register of 23 Oct 2026, connecting at APPLEFORD 400kV SUBSTATION (NGET). Status: Scoping.
- Customer
- APPLEFORD 2 RENEWABLES LTD
- Connection site
- APPLEFORD 400kV SUBSTATION
- Transmission owner
- NGET
- Technology
- Storage, Solar
- Capacity (TEC)
- 200 MW
- Agreement
- Direct Connection
- Status
- Scoping
- MW effective from
- 31 Oct 2037
- NESO project number
- PRO-002683