Didcot Battery
Didcot Battery is a demand, storage project of 100 MW in NESO's TEC Register of 23 Oct 2026, connecting at DIDCOT 400/132KV SUBSTATION (NGET). Status: Scoping. Gate 1.
- Customer
- DIDCOT BATTERY LIMITED
- Connection site
- DIDCOT 400/132KV SUBSTATION
- Transmission owner
- NGET
- Technology
- Demand, Storage
- Capacity (TEC)
- 100 MW
- Agreement
- Direct Connection
- Gate
- Gate 1
- Status
- Scoping
- MW effective from
- 31 Mar 2027
- NESO project number
- PRO-001468
Also at DIDCOT 400/132KV SUBSTATION
| Project | Technology | MW |
|---|---|---|
| Didcot A GTs | Gas | 100 |
| Didcot B | Gas, Storage | 1,705 |
| Didcot Energy Park | Storage | 300 |
| Didcot Road | Storage | 300 |
| PeakGen BEGA - Didcot | Oil & AGT (Advanced Gas Turbine) | 4 |
| Sutton Courtenay | Demand, Storage | 150 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.