Didcot A GTs
Didcot A GTs is a gas project of 100 MW in NESO's TEC Register of 23 Oct 2026, connecting at Didcot 400kV Substation (NGET). Status: Built.
- Customer
- RWE Generation UK Plc
- Connection site
- Didcot 400kV Substation
- Transmission owner
- NGET
- Technology
- Gas
- Capacity (TEC)
- 100 MW
- Agreement
- Embedded
- Status
- Built
- NESO project number
- PRO-000121
Also at Didcot 400kV Substation
| Project | Technology | MW |
|---|---|---|
| Didcot B | Gas, Storage | 1,705 |
| Didcot Battery | Demand, Storage | 100 |
| Didcot Energy Park | Storage | 300 |
| Didcot Road | Storage | 300 |
| PeakGen BEGA - Didcot | Oil & AGT (Advanced Gas Turbine) | 4 |
| Sutton Courtenay | Demand, Storage | 150 |
Source
- NESO TEC Register, National Energy System Operator, publication of 23 Oct 2026. NESO Open Data Licence.