Cranwell Solar & BESS Farm

Cranwell Solar & BESS Farm is a storage, solar project of 300 MW in NESO's TEC Register of 23 Oct 2026, connecting at Trent Valley South Connection Node C 400kV Substation (NGET). Status: Scoping.

Customer
TRIO POWER LIMITED
Connection site
Trent Valley South Connection Node C 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
300 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
30 Oct 2034
NESO project number
PRO-004952

Also at Trent Valley South Connection Node C 400kV Substation

ProjectTechnologyMW
Barnby Solar FarmStorage, Solar249.9
Bicker FenStorage, Solar400
CoddingtonStorage240
Elmya Foxdale BESSStorage800
Grantham GenerationStorage, Solar700
Grantham Solar Farm - RSLStorage, Solar810
Kinder PV & BESS StationStorage, Solar240
NatPower Navenby Energy ParkStorage1,000
Noventum NavenbyStorage, Solar249
Oak Holt SolarStorage, Solar400