Apley Head Farm is a storage, solar project of 240 MW in NESO's TEC Register of 23 Oct 2026, connecting at Trent Valley South Connection Node B 400kV Substation (NGET). Status: Scoping.

Customer
Queequeg Renewables Ltd
Connection site
Trent Valley South Connection Node B 400kV Substation
Transmission owner
NGET
Technology
Storage, Solar
Capacity (TEC)
240 MW
Agreement
Direct Connection
Status
Scoping
MW effective from
30 Oct 2035
NESO project number
PRO-003968

Also at Trent Valley South Connection Node B 400kV Substation

ProjectTechnologyMW
Cottam-Ryhall Solar & BESSStorage, Solar400
NatPower Allington Green Energy ParkStorage1,000
Natpower Thimbleby Green Energy ParkStorage1,000
Project Number 6Storage500
Project Number 8Storage500
Stack Hill Solar and StorageStorage, Solar350
TH Stow ManorStorage400
Worksop BESSStorage480

Source