Woodlands Farm

Woodlands Farm, Solar Inc Limited, is connected in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 12 MW, grid supply point Canterbury.

Customer
Solar Inc Limited
Status
Connected
Capacity
12 MW
Technology
Solar (Photovoltaic)
Flexible connection
No
Grid supply point
Canterbury
Bulk supply point
Canterbury South 33kV
Voltage
33 kV
Date connected
30 Mar 2015
In a connection queue
No
Row last updated by the DNO
13 Nov 2020
Licence area
South Eastern Power Networks (EPN) (as printed: the name and the code are two different licences)
Address
Calcott, Canterbury
Postcode
CT3 4NB
Export MPAN
1900091207133

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.