Wharf Road

Wharf Road, EL (SLH) Limited, is accepted to connect in UK Power Networks's Embedded Capacity Register of 14 Oct 2026 at 40 MW, grid supply point Tilbury.

Customer
EL (SLH) Limited
Status
Accepted to connect
Capacity
40 MW
Technology
Gas (Gas turbine (OCGT))
Flexible connection
No
Grid supply point
Tilbury
Voltage
132 kV
Date accepted
7 Oct 2018
Target energisation
13 Mar 2025
In a connection queue
Yes
Row last updated by the DNO
12 Jul 2024
Licence area
EPN
Address
Stanford-Le-Hope
Postcode
SS17 0EH

A distribution project is the rows of one DNO’s Embedded Capacity Register that agree on licence area, customer site, grid supply point and customer; no DNO publishes a reference on every row. Each row’s capacity is the DNO’s own figure for that row and rows are never summed. Accepted to connect is the DNO’s status; a flexible (ANM) connection’s capacity is not firm. A target energisation date is as published, a planned date. Distribution MW are never added to TEC.